The heating networks in Yunusabad will be repaired by 2025

Society
13
Heat networks in Yunusabad will be repaired by 2025
The extensive repair work on the heat networks in the Yunusabad district will be completed by August 30, 2025. This was reported by Upl.uz.

This was announced by Veolia Energy Tashkent. As part of the planned repair and restoration work, the following activities are being carried out in the underground engineering collectors and heat networks of the district.

In the area from the Yunusabad district tax office to house 1a on Oluy Street, pipes with a diameter of 500 millimeters are being replaced over a length of 2500 meters. The work is being carried out with the help of cranes through installation windows.

Additionally, heat networks with a diameter of 500 millimeters are being renewed over a length of 280 meters in the direction from the administrative building of the Tashkent University of Information Technologies to the Central Bank NBU building. Here, A.

At the intersection of Temur and Hakimzoda streets, near the university dormitory, networks with a diameter of 300 millimeters are being replaced over a distance of 200 meters. Also, heat networks with a diameter of 500 millimeters are being renewed over a length of 450 meters along the pedestrian path from the Shahriston restaurant area towards the railway.

Similarly, networks of the same diameter are being replaced over 450 meters on the road from the People's Bank building to the Yunusabad district criminal court building. All designated work is planned to be fully completed by August 30, 2025.

This repair work is aimed at improving the reliability and efficiency of the heating supply in the area. Users are asked for understanding and patience regarding temporary inconveniences.

[lang=ru,en]

Partners news

[/lang]

Similar news

Which streets will be closed due to the Eid prayer in Tashkent?
Which streets will be closed due to the Eid prayer in Tashkent?
In order to conduct the Eid prayer at a high level and in an orderly manner, create necessary conditions for citizens, and ensure their safety, a number of streets and roads in the capital will
Society 06:26, 29-03-2025
In Shaykhontohur, there will be a hot water outage in August
In Shaykhontohur, there will be a hot water outage in August
Veolia Energy Tashkent company announced planned maintenance work in the Shaykhontohur district as the operator of the capital's heating supply system. This was reported by Upl.uz. In this
Society 22:39, 4-08-2025
Why did Russia occupy southern Ukraine so quickly?
Why did Russia occupy southern Ukraine so quickly?
On February 24, 2022, at 4 a.m., the Russian army began its attack on Ukrainian territory. The advance was conducted simultaneously in several directions: south, east, and north. However, it was in
World 13:41, 28-02-2025
The "Manchester City" club published an article about Abduqodir Husanov that has not been published anywhere else
The "Manchester City" club published an article about Abduqodir Husanov that has not been published anywhere else
“Manchester City” club published an article on its social media page enriched with previously unpublished information about the young footballer Abduqodir Husanov, who quickly captured the hearts of
Sports 22:33, 14-03-2025
Veolia has suspended tests in the heating networks
Veolia has suspended tests in the heating networks
Veolia Energy Tashkent announced that it has temporarily suspended the hydraulic tests of the heating networks scheduled from May 30 to July 17, 2025. This was reported by Upl.uz. This decision was
Society 20:07, 10-07-2025